Project – Removal of failed timber pew bases and reinstatement with insulated limecrete floor screed and matching tile scheme. Removal of low level cementitious render and re-rendering in lime mortar including joinery repair and adjustment to several pews.
For the PCC of All Saints Church with Oliver West & John Scott Architects Ltd
- pews and pew base removed, limecrete floor to be cast
- re-tiling #1
- re-tiling #2
- re-tiling #3 with new limecrete floor and plaster with edge gap to allow moisture evaporation at base of wall
- completed tiling #1 with lime plaster awaiting limewash
- completed tiling #2 with re-fixed pew